1 / 16
20 ENDRESS VR - W 400 - Central heating system
- Current bid
- Status
€
Total bid amount
See total breakdown
Total bid amount
See total breakdown
€
Max bid amount
See total breakdown
Max bid amount
See total breakdown
Lot specifications
- Quantity
- 1
- Margin
- No
- Brand
- ENDRESS
- Type
- VR - W 400
- Year of build
- 20
- Serial number
- EN1453
- Heating capacity
- 400kW
- Own weight
- 3500kg
- Total dimension L
- 4500mm
- Total dimension W
- 1500mm
- Total dimension Height
- 2500mm
- HS Code
- 84031010
- Terms of delivery
- Ex foundation-unpackaged
Description
For sale is a powerful wood-burning system from the manufacturer ENDRESS, type VR-W 400, built in 2012.
The system was used to generate heat from biomass (e.g. wood chips) and is ideal for heating systems in commercial, industrial or local heating networks.
Technical data:
• Type: ENDRESS VR-W 400
• Year of manufacture: 2012
• Power: 400 kW
• Water capacity: 1,800 litres
• Operating temperature (max.): 95 °C
• Permissible operating overpressure: 3 bar
• Boiler class: 3
• Designation according to the nameplate: wood-burning system
• Fuel supply: possible
via several screw conveyors with electric motors
Accessories:
• Exhaust gas purification unit
• Membrane pressure expansion vessel "reflex G"
• Various drive units
The system was used to generate heat from biomass (e.g. wood chips) and is ideal for heating systems in commercial, industrial or local heating networks.
Technical data:
• Type: ENDRESS VR-W 400
• Year of manufacture: 2012
• Power: 400 kW
• Water capacity: 1,800 litres
• Operating temperature (max.): 95 °C
• Permissible operating overpressure: 3 bar
• Boiler class: 3
• Designation according to the nameplate: wood-burning system
• Fuel supply: possible
via several screw conveyors with electric motors
Accessories:
• Exhaust gas purification unit
• Membrane pressure expansion vessel "reflex G"
• Various drive units
Remarks
The plant is in an overall functional condition and was operated until the end. However, the vault of the furnace shows clear signs of wear and should be renewed to ensure safe and efficient operation over time.
The screw conveyor was renewed in 2024 and is in very good condition.
A welding repair was carried out on the fuel insertion, which has held reliably so far. However, it is recommended to check this area regularly during operation, as it is a stressed and heat-stressed zone.
The screw conveyor was renewed in 2024 and is in very good condition.
A welding repair was carried out on the fuel insertion, which has held reliably so far. However, it is recommended to check this area regularly during operation, as it is a stressed and heat-stressed zone.